(524f) CO2 Post Combustion Capture Operational Flexibility and Scale-Up For Power Plants
AIChE Annual Meeting
2013
2013 AIChE Annual Meeting
Topical Conference: CO2 Capture
Amine Scrubbing for CO2 Capture: Dynamic Modeling and Systems Analysis
Wednesday, November 6, 2013 - 5:20pm to 5:45pm
CO2 Post Combustion
Capture Operational Flexibility and Scale-up for Power Plants
Prachi Singh, John Davison
International Energy Agency Green House Gas R&D
Programme (IEAGHG), The Orchard Business Centre, Stoke
Orchard, Cheltenham, GLOS UK, GL52 7RZ, UK
1.Introduction
Several governments
and international organizations have set 2020 as the target for broad
commercial deployment of Carbon Capture and Storage (CCS). With this target in
mind, it is clear that the initial commercial and full scale capture plants
will have to be based on currently available technologies. These commitments
and agreed targets create an important role for the solvent‐based
post‐combustion capture technology, which is
considered to be the most mature of the capture technologies available today. CO2
Post combustion capture technology provides a retrofit possibility and is
already available on relatively small industrial scale. Moreover now a days
existing and new power plants must face the challenges of the liberalized
electricity market and the requirement to cover intermediate and peak load
constraints, in order to respond to the daily and seasonal variation of the
electricity demand. Most studies undertook CO2 post combustion
capture at power plant base load operation, but it is now clear that CO2
post combustion capture technology will also need to be able to respond to the
requirements of the new liberalized electricity market. Therefore, in this
work, current capabilities of conventional Ultra Supercritical Pulverised Coal
(USCPC) and Natural Gas Combined Cycle (NGCC) fired power plants, without and
with conventional solvent‐based CO2 post combustion capture
technology to operate flexibly in response to the demand of the electricity
market and factors that may constrain the operation flexibility and cost
implications were evaluated by process modelling (IEAGHG 2012).
Scale-up issues
related to conventional solvent‐based CO2
post combustion capture technology for Supercritical Pulverized Coal (SCPC)
900MWe and NGCC 809MWe power plant are also evaluated in this work (IEAGHG
2013). However due to the different scope requirement for operational
flexibility and scale-up study, the design of solvent based CO2 post
combustion capture process may not be identical for both studies. The
difference in the CO2 capture process may differ mainly in the heat
integration, absorber design and solvent characteristics. Although this
difference will not change the main outcome on operation flexibility and scale
up issues for post combustion capture technology.
2.CO2
Post Combustion Capture Technology Operational Flexibility
The introduction of
post combustion CO2 capture may impose additional constraints on the
start-up and fast load changing of a power plant but techniques are available
to overcome these constraints. In an NGCC plant the gas turbine starts up more
rapidly than the heat recovery steam generator (HRSG) and the steam turbine.
The regenerator in the CO2 capture plant requires steam from the
HRSG or steam turbine and the regenerator needs to be heated to its operating
temperature. To avoid constraints on start-up time and to avoid CO2
emissions during start up, the CO2 absorber could be operated using
lean solvent from a storage tank and the CO2 rich solvent from the
absorber would be stored and fed to the regenerator later. This would enable an
NGCC or USCPC plant with CO2 capture to start up and change load as
quickly as a plant without capture. This technique is evaluated in this work is
discussed later in this paper.
2.1.Turn off or turn down of CO2 capture
The net power output
of a plant could be increased by turning down or turning off the CO2
capture and compression units and emitting more CO2 to the
atmosphere. The ability of a plant with CO2 capture to ramp up power
output could in principle be better than that of a plant without capture if the
load of the CO2 capture unit was reduced at the same time as the
load of the power generation unit was increased. This work assessed the option
of turning off CO2 capture but various intermediate options
involving turning off or turning down parts of the CO2 capture plant
may also be attractive. Turning down or turning off capture would increase
emissions of CO2 to the atmosphere so regulations would have to
permit CCS plants to emit more CO2 during times of peak power demand. Turning down or turning off CO2 post
combustion capture would reduce the plant's internal consumption of electricity
and the low pressure steam that would otherwise be consumed by the CO2
capture unit could be used to further increase the net power output, provided
the plant was built with the necessary extra low pressure turbine capacity.
Table 1, Turning off
CO2 capture plant
NGCC
|
USCPC
|
|
Increase in power output with no capture, %
|
15.9
|
27.4
|
Thermal efficiency, %
|
||
Reference plant with capture
|
50.6
|
34.8
|
Plant with capability to turn off capture
|
50.2
|
34.2
|
Plant with capture turned off
|
58.6
|
44.3
|
Capital cost
|
||
Change in cost per kW of normal output, %
|
+5.8
|
+3.9
|
Change in cost per kW of peak output, %
|
-8.7
|
-18.5
|
Cost of extra peak power capacity, ?/kW
|
354
|
322
|
CO2 emissions
|
||
Tonnes CO2 per MWh of extra peak power |
2636
|
2944
|
It can be noticed
from Table 1 that having the capability to turn off capture increases the
capital cost of the plant (per kW of normal power output), mainly because of
the need for greater steam turbine capacity, but the cost per kW of peak power
output is lower. The net capital cost per kW of extra peak power generation
capacity is relatively low, probably less than the cost of other types of peak
generation capacity.
2.2.Solvent storage
Solvent from post
combustion capture can be stored during times of peak power demand for
regeneration during times of lower power demand. This reduces the requirement
for other peak generation capacity. The extra generation during peak times
would have low CO2 emissions, unlike the alternatives of by-passing
CO2 capture or using peaking plants such as simple cycle gas
turbines without CCS.
Table 2, Storage of
post combustion CO2 capture solvent
Power plant type
|
NGCC
|
USCPC
|
NGCC
|
USCPC
|
|
Storage scenario
|
Weekly
|
Weekly
|
Daily peak
|
Daily peak
|
|
Hours per week of peak output
|
80
|
80
|
10
|
10
|
|
Increase in power output at peak times, %
|
6.2
|
4.8
|
12.1
|
22.2
|
|
Thermal efficiency, %
|
|||||
Reference plant efficiency, 100% load |
50.6
|
34.8
|
50.6
|
34.8
|
|
Reference plant time weighted average efficiency |
50.6
|
33.6
|
50.6
|
33.6
|
|
Storage plant time weighted average efficiency |
45.3
|
33.5
|
50.5
|
33.6
|
|
Capital cost
|
|||||
Change in cost per kW of normal output, % |
+19.6
|
+6.1
|
+9.3
|
+5.8
|
|
Change in cost per kW of peak output, % |
+12.6
|
+1.2
|
-2.6
|
-13.5
|
|
Cost of extra peak generation, ?/kW |
3116
|
2891
|
752
|
589
|
|
Solvent storage
|
|||||
Quantity of solvent storage, 103m3 |
286
|
199
|
30
|
46
|
|
Two operating
scenarios described below were assessed in this study as an illustration but it
is recognised that in reality power plant operations will depend on many
external factors which may change during the operating life of a plant. The
?weekly' and ?daily' scenarios involve different amounts of solvent storage and
peak load operation. It can be noticed from Table 2, that the solvent storage
has very little effect of the thermal efficiency except for the NGCC weekly
scenario, in which one of the gas turbines has to operate at minimum
environmental load at off-peak times to regenerate solvent. The solvent storage
tanks are conventional sized tanks as used at oil refineries but they are
nevertheless large, particularly in the weekly scenario. In the weekly scenario
the capital cost per kW of additional peak generation capacity is greater than
the cost of the reference power plant, which indicates that this scenario is
unlikely to be attractive. In the daily scenario the capital cost per kW of
additional peak generation capacity is less than the cost of the reference
plant but it is probably higher than the cost of the leading alternative
technology for peak load generation, namely simple cycle gas turbines. Solvent
storage may be attractive in this scenario, depending on fuel prices, carbon
emission costs and the electricity price profile.
3.CO2
Post Combustion Capture Technology Scale-up Issues
CO2 post
combustion capture design cases for SCPC and NGCC were reviewed to identify the
major issues that will likely be faced when moving from the current
demonstration scale to constructing and operating large commercial scale units.
In general, there appear not to be any major risks which have not been
addressed either in power generation or elsewhere in the heavy industrial
sector. Integration of the each component of the CO2 capture
facility at large scale and incorporation into existing power plant designs may
represent the largest challenge. The main issues related to scale up for post
combustion capture process which emerged in the study are construction of
absorber and regenerator, stiffing of the boiler, ductwork and flue gas equipment,
bypass of flue gas, increase in gas turbine back pressure, amine emission
issues etc.
4.References
IEAGHG, Operating Flexibility of Power Plants
with CCS, 2012/6, June, 2012.
IEAGHG, Post Combustion CO2
Capture Scale-up Study, 2013/05, February 2013.
Topics
Checkout
This paper has an Extended Abstract file available; you must purchase the conference proceedings to access it.
Do you already own this?
Log In for instructions on accessing this content.
Pricing
Individuals
AIChE Pro Members | $150.00 |
AIChE Graduate Student Members | Free |
AIChE Undergraduate Student Members | Free |
AIChE Explorer Members | $225.00 |
Non-Members | $225.00 |