(118b) Ethylene Plant Precommissioning
AIChE Spring Meeting and Global Congress on Process Safety
2007
2007 Spring Meeting & 3rd Global Congress on Process Safety
Ethylene Producers Conference
Ethylene Plant Maintenance - Furnace Maintenance Technology Forum
Thursday, April 26, 2007 - 9:00am to 9:25am
Pre-commissioning is a vital phase in the overall ethylene plant construction /start-up schedule. The respective assignments and responsibilities will be agreed and allocated between the licensor/engineering company, the construction contractor, the related equipment vendors and the client. Pre-planning of the entire pre-commissioning and commissioning phases is essential at an early stage in the basic design phase. Exact definitions of the respective mechanical completion, pre-commissioning, commissioning and start-up activities are essential at the outset of the project. Pre-commissioning typically begins up to 9 months prior to actual start-up. A key aspect is the designation of the respective ISBL/OSBL plant systems, their post-construction inspection and delivery, and the correct involvement of all parties. Corresponding budgetary costs must be estimated and approved.
An essential element of successful pre-commissioning is the precise definition of the activities involved and the approved documentation to validate related tests and results.
The specific activities involved include: ? Air blowing ? Steam blowing ? Water flushing ? Vessel cleaning ? Chemical cleaning ? Speciality cleaning, eg HP water blasting ? Equipment inspection ? System dryout ? Critical instrumentation function testing
Conscientious completion of the above pre-commissioning activities sets the stage for successful pre and post start-up results.