Four Major Gaps That Are Preventing Most Companies Worldwide from Achieving Excellent Process Safety Performance
AIChE Spring Meeting and Global Congress on Process Safety
2017
2017 Spring Meeting and 13th Global Congress on Process Safety
Global Congress on Process Safety
Case Histories and Lessons Learned - GCPS Joint Session
Wednesday, March 29, 2017 - 6:00pm to 6:30pm
Various accidents in the past such as the Formosa Plastics propylene explosion in 2005 show that small leaks or fires can escalate to cause damage to the unit and also escalate to cause damage to adjoining units. Inadequate separation between units, inadequate active and passive protection of structures and equipment, particularly for jet fires, inadequate isolation and blowdown measures, inadequate specification of safety critical elements such as ESDVs and flare headers are some of the causes for escalation. To minimize asset loss and injuries, facility siting and plant layout need to incorporate a systematic assessment of escalation risk to ensure mitigation measures are identified and incorporated.
Escalation risks can be assessed following a consequence-based approach or a risk-based approach incorporating both frequency and consequence estimation. While consequence-based analysis is a simple and easy tool to use, the selection of credible failure scenarios can become a subject of debate - many projects have adopted a generic 1â or 2â hole size as the basis for analysis whereas some have considered larger hole sizes. Given the increased size of piping and equipment due to larger throughputs, a 1â or 2â hole size may be considered as insufficient. The alternative is to follow a risk based approach wherein all leak sizes are modelled together with mitigation system failure, directionality and ignition/explosion probability to determine the cumulative likelihood of a damaging fire or explosion event. Such an approach would typically be based on a target frequency threshold of 1E-4 per year. This method is subject to the usual uncertainties associated with a frequency assessment including those associated with failure frequency data and the various event probabilities.
Case studies for onshore installations handling hazardous substances are presented considering both risk-based and consequence-based approaches for comparison. The case studies also illustrate how mitigation measures can be designed based on such an analysis to reduce the risk of escalation. Examples of mitigation measures considered include increased spacing between process units, increased spacing between sections of a large process unit by segregated fire zones, spill containment, fire and gas detection, isolation and blowdown, and active and passive fire protection. The case study results are also compared with typical deterministic spacing tables, which are commonly used for plot plan development, whereby recommendations are provided to minimize the risk of escalation early on during the initial plot plan development stage of the project.